Jurisdiction: Botswana
Court: Court of Appeal | Date of Ruling: 1 February 2013

The Court of Appeal of Botswana granted Air Botswana’s application to excuse a three-week delay in paying security for costs. Although the court questioned several arguments advanced by Air Botswana, it found that the scope of the arbitrator’s mandate presented an arguable case.
I. Case Information
| Field | Details |
|---|---|
| Citation | NIPJD/BW/CACGB-105-12 |
| Case Name | Air Botswana v. Lebang and Others |
| Country / Jurisdiction | Botswana |
| Court | Court of Appeal of Botswana, sitting at Gaborone |
| Appeal No. | CACGB-105-12 |
| Lower Court Case No. | Industrial Court Case No. APP-28-10 |
| Date of Ruling | 1 February 2013 |
| Applicant | Air Botswana |
| Respondents | Thembo Lebang and 13 Others |
| Judge | E. W. M. J. Legwaila J.A. |
| Counsel for the Applicant | M. M. Chilisa |
| Counsel for the Respondents | J. B. Akoonyatse |
| Nature of Proceedings | Application for condonation of late payment of security for costs |
| Focus Areas | Civil Procedure; Labour and Employment Law; Arbitration; Judicial Review; Security for Costs |
| Outcome | Delay in paying security for costs condoned |
II. Background
The underlying dispute concerned overtime entitlements for Air Botswana drivers. The parties voluntarily referred the dispute to arbitration.
The arbitrator directed Air Botswana to calculate and pay overtime from December 2000. The award also referred to implementing a three-week shift cycle with a ceiling of 144 hours, with additional hours treated as overtime. The award was to be implemented within 30 days.
Following proceedings in the Industrial Court, Air Botswana pursued an appeal. However, it paid security for costs three weeks late and applied for condonation.
Air Botswana attributed the delay to an oversight by its legal representative, arising largely from the parties’ efforts to settle the dispute without pursuing the appeal. The respondents did not oppose the application and indicated that they would abide by the court’s decision.
III. Issues for Determination
- Whether Air Botswana had shown sufficient cause to excuse its late payment of security for costs.
- Whether its proposed appeal presented an arguable case.
- Whether the arbitrator’s directions on overtime arguably exceeded the scope of the matters submitted to arbitration.
IV. Court’s Decision and Reasoning
Condonation required consideration of the circumstances as a whole.
Relying on Melane v. Santam Insurance Co. Ltd, the court explained that condonation involves judicial discretion and fairness to both sides. Relevant considerations include the length of the delay, the explanation offered, prospects of success, the importance of the case and the respondents’ interest in finality.
These factors must be considered together rather than treated as individually decisive.
Review and appeal serve different purposes.
The court observed that Air Botswana’s original grounds of appeal largely challenged the arbitrator’s evaluation of evidence. Those complaints concerned the merits and reflected a misunderstanding of the distinction between review and appeal.
An appeal generally challenges the correctness of a conclusion on the facts or law. Review concerns defects in the process, including jurisdictional errors and procedural irregularities.
The challenge to the timing of the arbitration referral was rejected.
Air Botswana argued that the dispute had not been referred within a reasonable time because it concerned matters dating back to 2000.
The court noted that the referral was voluntary and that Air Botswana had not raised this objection when agreeing to arbitration. It rejected the attempt to rely on the timing of the referral at this stage.
The scope of the arbitrator’s mandate presented an arguable case.
Air Botswana argued that the arbitrator was authorised to determine arrears of overtime, not future overtime entitlements. In their written submissions, the respondents conceded that the arbitrator had exceeded his mandate in this limited respect.
The court questioned that interpretation. Reading the award as a whole, it considered that the disputed direction could refer to overtime from December 2000 up to implementation of the award, rather than an indefinite future period.
Alternatively, the court reasoned that the parties’ continuing employment relationship could support a broader understanding of the mandate, allowing a solution that also addressed their future working relationship.
Nevertheless, the court concluded that the issue presented an arguable case and granted condonation.
V. Final Order
- Security for costs — The delay in payment was condoned.
VI. Significance
This ruling illustrates the factors considered when a Botswana court is asked to excuse procedural noncompliance. It also explains the distinction between challenging an arbitral award on its merits and challenging the arbitrator’s jurisdiction or procedure.
The court’s discussion of the arbitration issues arose while assessing the condonation application. The ruling did not finally determine the substantive appeal.
VII. Cases Cited in the Ruling
- Melane v. Santam Insurance Co. Ltd, 1962 (4) AD 531 — Factors governing the exercise of discretion in condonation applications.
- Raphethela v. Attorney-General, [2003] 1 BLR 591 — Distinction between review and appeal.
- Tawana v. The State, [1984] BLR 272 (CA) — Referenced in assessing whether an arguable case had been shown.
VIII. Full Ruling
Read or download the full ruling (PDF)
